If a special inspector observes a non-conformance that is about to be covered up, what is the correct course of action?

Prepare for the Special Inspection GR Exam. Achieve confidence with flashcards and multiple-choice questions, each with hints and explanations. Get exam-ready now!

In the context of special inspections, when a non-conformance is observed that might be hidden or covered up, the correct course of action involves notifying the contractor first, followed by informing the building official and the registered design professional. This approach is critical because it allows for immediate communication and rectification of the issue at the source, which is with the contractor who has the responsibility to address the non-conformance.

By notifying the building official and the registered design professional afterward, the special inspector ensures that all relevant parties are aware of the potential issue and can take the necessary steps. This not only emphasizes the importance of addressing defects promptly but also aligns with communication protocols established in building and inspection regulations.

Taking these actions helps maintain the integrity of the construction process and compliance with safety and quality standards, ensuring that non-conformances do not compromise the overall project.