What should the contractor do if a non-conforming item is identified?

Prepare for the Special Inspection GR Exam. Achieve confidence with flashcards and multiple-choice questions, each with hints and explanations. Get exam-ready now!

When a non-conforming item is identified, it is essential for the contractor to notify the special inspector immediately. This is critical because the role of the special inspector is to ensure compliance with construction documents, standards, and regulations. By informing the special inspector, the contractor initiates the process of assessing the non-conformance, which may involve documenting the issue and determining the necessary corrective actions.

Addressing non-conformance appropriately helps maintain the integrity of the construction process and ensures that any deviations from the approved plans are rectified in a timely manner. Notifying the special inspector ensures that any necessary inspections, reviews, or actions can be taken, thereby preventing potential issues down the line that could affect the safety and quality of the construction project.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy