Which of the following tasks is not required of the special inspector prior to arriving at the job site?

Prepare for the Special Inspection GR Exam. Achieve confidence with flashcards and multiple-choice questions, each with hints and explanations. Get exam-ready now!

The task that is not required of the special inspector prior to arriving at the job site is meeting with the contractor. While it's beneficial for the inspector to have discussions with the contractor regarding the project and its specific needs, this meeting is not a formal requirement established within the guidelines for special inspections.

In contrast, reviewing the statement of special inspections, discussing reporting frequency with the building official, and reviewing plans and specifications are critical preparatory tasks. These activities ensure that the special inspector is well-informed about the expectations and requirements associated with the project, enabling effective oversight and compliance during construction activities. They help establish a clear understanding of the scope of inspections needed and when they should take place in relation to the project timeline. Meeting with the contractor, while useful for communication and coordination, does not fall into the essential pre-arrival duties outlined for special inspectors.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy