Who can issue a notice of non-compliance during a special inspection?

Prepare for the Special Inspection GR Exam. Achieve confidence with flashcards and multiple-choice questions, each with hints and explanations. Get exam-ready now!

The correct response indicates that both the Registered Design Professional (RDP) and the special inspector have the authority to issue a notice of non-compliance during a special inspection. This is based on their roles and responsibilities within the inspection process.

The RDP is typically responsible for ensuring that the design meets all applicable codes and standards, and may notice discrepancies during construction or inspection. The special inspector, on the other hand, is tasked with monitoring specific aspects of the construction process to ensure compliance with the construction documents and relevant regulations. When either the RDP or the special inspector identifies non-compliance with the construction standards, they are empowered to issue a notice, which is an important part of maintaining project integrity and adherence to established guidelines.

This collaborative approach ensures that multiple qualified parties are involved in overseeing compliance, enhancing accountability and minimizing risks associated with construction errors or omissions.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy